twin-shaft compulsory mixer concrete mixing station installation

Program process catalog:
the preparations prepared: required to prepare each member installed around the site cleared of debris, land leveling, to ensure smooth flow of vehicles.
the concrete batching plant installation floor plan
the base map retest: carefully review all design drawings provided by the manufacturer, with the construction site, the basis for determining the center position of the axis and the relevant reference point, good embedded positioned preparations. Provide design drawings shown using external control law implementation retest according to the manufacturer. The use of closed transfer control to determine the elevation; axis, retest level should be combined with the construction program, the relationship between the construction site layout plan of the relevant processes and device structures, aims to reduce errors, ensure project quality and progress.
the cement silo installation: stand assembly, stand in place, warehouse body attachment assembly, warehouse body lifting
Installation Host: Install Host legs, install walkways, positioning, metering assembly floor assembly, installation receiving hopper.
complete concrete batching plant Installation of six, the control room and the stent
Installation seven ingredients machine
Installation of eight screw machine
Installation Nine, waterways, gas and additives
concrete batching plant(60m3/h) wiring debugging
metering system acceptance
emergency plans
security measures
concrete batching plant equipment maintenance